In this text · 5 parts
Stages that never fully end
The diagnosis was delivered, but the committee asks for adjustments. They are made, and others appear. No one knows whether the stage is closed or whether the next one can start. In the end, the decision is made out of fatigue or the calendar, not because the deliverable meets something verifiable.
The origin is usually the same: it was agreed what would be delivered, but not when it would be accepted. Without that condition, every review opens a new conversation about what was expected. That is why, in a sound method, each stage closes with two things: a deliverable and a clear criterion for accepting it.
The acceptance criterion is written before the stage starts. Writing it at the end is negotiating, not verifying.
Five stages, each with its deliverable and criterion
As an example, this is the five-stage framework used by our consulting practice. Each engagement adapts it to its scope, but the logic stays the same: one objective, one deliverable and one condition for accepting it.
| Stage | Deliverable | Accepted when… |
|---|---|---|
| Understand | Situation map and agreed scope | The team recognizes its operation on the map. |
| Diagnose | Diagnosis with findings and evidence | Each finding is backed by evidence. |
| Design | Design, roadmap and indicators | Owners, dates and baseline are defined. |
| Run | Progress reports with traceability | Each deliverable is reviewed against what was agreed. |
| Assess | Closing report and recommendations | Indicators are read with their period and context. |
Notice that none of these criteria says “to the client’s satisfaction” or “approved by the committee”. Each describes something that can be checked: whether the team recognizes itself in the map, whether each finding has its evidence, whether there are owners and dates. Formal approval comes afterwards, as proof that the condition was met.
How to write a good criterion
A useful criterion meets four conditions. If any is missing, sooner or later it becomes a dispute.
Observable
Describe something that can be seen or verified, not a feeling. “Each finding has evidence” can be checked. “The diagnosis is complete” cannot.
Verifiable with evidence
It states what evidence shows it was met: a minute, a record, a review with the team. If there is no way to prove it, it is not a criterion.
With an owner
State who verifies and who gives acceptance. They may be different people, but both must be named.
Agreed upfront
It is discussed and signed at the start of the stage, when there is not yet a deliverable to defend or object to.
A hypothetical example shows it better. “The process mapping will be approved by the area” leaves everything open. “Each process in the scope has its documented flow, reviewed in session with the people who operate it, and with comments resolved or recorded in the minutes” says what is reviewed, with whom and what support remains. The second version is longer, but it avoids weeks of back-and-forth.
What a useless criterion looks like
The classic formula is “received to the client’s satisfaction”. It sounds formal, but it does not say what the deliverable must meet. It leaves acceptance in the hands of the reviewer’s perception, which can change over time or with people.
It depends on a preference
Expressions such as “adequate”, “of quality” or “sufficient” without defining what they mean in this case.
It only requires presence
“The sessions were held” tells you there was activity, not that the stage achieved what it set out to do.
No associated evidence
If no one knows which document proves compliance, acceptance rests on someone’s word.
It accumulates at closing
A single criterion for the whole project, reviewed at the end, prevents spotting in time a stage that was not met.
To fix it, ask: what would someone who did not take part need to see to agree that this is finished? The answer is usually the missing criterion.
What to do when it is not met
That a criterion is not met is not a failure. It is information. What matters is handling it with the same order with which it was defined.
Record what was missing
Record, with evidence, which part of the criterion was not met. “Returned” is not enough.
Separate cause from symptom
Check whether the problem lies in the deliverable, in the information available or in a poorly framed criterion.
Decide by date
Correct and review again, accept with recorded observations, or adjust the criterion by formal, documented decision.
What is not advisable is leaving the stage in limbo: neither accepted nor returned, while the next one has already started. That limbo is what later appears as a pending item with no owner in the closing report.
Bring the project’s list of deliverables to the next kickoff meeting, with the acceptance criterion for each one written in a sentence. If any of them says “to the client’s satisfaction”, that is the first one to rewrite.
To bring to the meeting
What is worth having resolved before the next meeting.
0 of 5
Mark what you have already resolved.
NoteGeneral guide. Each organization should adapt it to its context.